Wednesday, February 3, 2016

Construction Day 27: Started Insulation

Our garage, front porch and basement are now poured and the basement is framed! They started insulation and should be done by the end of next week. Ryan Homes does not insulate the garage walls that are not interior walls so our PM told us we can do that ourselves if we would like. Shout out to Scott and Ken for helping! :)



























Saturday, January 23, 2016

Construction Day 22: Roof, HVAC and Plumbing

This week they put on our roof so our house is now considered enclosed. They completed our HVAC, plumbing and poured our basement. When we got there today we couldn't get into the house so I could only take a few pictures from the front window that was cracked open. They have heaters in the garage because they are going to pour that on Monday. Next week the framers are coming to frame the basement and they are installing our electric. Our PM said we may have our Pre-Drywall meeting on Friday if everything goes perfect this week! It may be the following Monday but we are cruising right along! We will know the week we move in once the drywall is up. At this moment we are slated to move in the third week of March. 







Saturday, January 16, 2016

Construction Day 17: Finished Framing

We have a house!! Next week they stack our roof, plumbing and HVAC rough in and hopefully electricity. 

 Foyer


Dining Room




 Butler's Pantry and Pantry


Kitchen and Morning Room

Family Room



 Kitchen and Morning Room


 Guest Room


 Balcony


 Guest Room

 Guest Room

 Master

 Master Shower


Master



 Foyer