This week they put on our roof so our house is now considered enclosed. They completed our HVAC, plumbing and poured our basement. When we got there today we couldn't get into the house so I could only take a few pictures from the front window that was cracked open. They have heaters in the garage because they are going to pour that on Monday. Next week the framers are coming to frame the basement and they are installing our electric. Our PM said we may have our Pre-Drywall meeting on Friday if everything goes perfect this week! It may be the following Monday but we are cruising right along! We will know the week we move in once the drywall is up. At this moment we are slated to move in the third week of March.
Saturday, January 23, 2016
Saturday, January 16, 2016
Construction Day 17: Finished Framing
We have a house!! Next week they stack our roof, plumbing and HVAC rough in and hopefully electricity.
Foyer
Dining Room
Butler's Pantry and Pantry
Kitchen and Morning Room
Family Room
Kitchen and Morning Room
Guest Room
Balcony
Guest Room
Guest Room
Master
Master Shower
Master
Foyer
Tuesday, January 12, 2016
Construction Day 13: First Floor Framing
Joe and I stopped by our lot after work today because we knew they were starting to frame this week. Despite the frigid weather we've been having these past few days, they have our first floor up!
Garage
Front door and dining room windows
Dining room
Morning Room
My office
Family room
Family room windows
Fireplace
Kitchen
View of family room and door to outside from morning room
Door to basement
Dining room
Dining room
Pantry
Subscribe to: